How to measure your area
Measure length and width in feet and depth in inches. For odd shapes, break the area into rectangles and add them up, or measure the square footage another way and use the square-feet option. A pad for an RV, a backyard to lower for drainage, or a lot to fill all work the same way.
One cubic yard is 27 cubic feet: a 9 by 9 foot area 4 inches deep is exactly one yard.
Bank, loose and compacted yards
Dirt in the ground is bank volume. Dig it up and it fluffs, or swells, into a larger loose volume, which is what fills a truck. Compact it back into a pad or trench and it shrinks again. That is why haul-off is always more truckloads than the hole looks like, and why fill for a compacted pad takes more material than the finished volume.
| Material | Typical swell when dug | What it means |
|---|---|---|
| Sand or sandy wash | About 15% | Little fluff, but it caves in trenches |
| Typical desert soil | About 25% | Our default for most Tucson lots |
| Clay | About 35% | Sticky when wet, hard when dry |
| Caliche or broken rock | About 50% | Breaks into chunks with lots of voids |
Truckloads and tons
Truck capacity is loose volume. A small dump truck typically carries around 5 cubic yards and a 10-wheel dump truck around 12, depending on the bed and the weight of the material. Suppliers sell ABC, DG, sand and rock by the ton, so the calculator estimates weight too. Use your supplier's weight per yard when you order.
Ordering for a trench instead? The trench calculator handles bedding sand and backfill. For hauling and delivery, see hauling, fill dirt and material delivery.
Questions we get about this
How many cubic yards are in a dump truck load?
It depends on the truck. Small dump trucks typically haul around 5 cubic yards, and 10-wheel trucks around 10 to 14, limited by weight as much as bed size. Heavy material like wet clay, rock or ABC fills the weight limit before the bed is heaped.
Why do I need more fill than the size of the hole?
Fill placed for a pad or trench is compacted, so it ends up denser than the loose material delivered. You need enough loose material to end up with the compacted volume, plus a little extra for grading to final elevation.
Should I order by the ton or by the cubic yard?
Order the way the supplier sells, which in Arizona is usually by the ton for ABC, DG, sand and rock. Use the cubic yards from this calculator and the supplier's weight per cubic yard for that material to convert.