Arizona 811: What to Do Before You Dig in Tucson

Request a locate through 811 or arizona811.com at least two full working days before you dig, mark your dig area in white, and wait for every utility to mark or clear it. The utilities will not mark your own private lines, so those need a separate plan.

Key points

  • Request the locate at least two full working days before digging; weekends and legal holidays do not count.
  • Marks are valid for 15 working days, so re-request before they expire.
  • Within 24 inches of a marked line, expose it with hand tools.
  • Excavators must white-line the dig area; only an owner digging on their own single-family property is exempt.
  • Utilities do not mark private, customer-owned lines such as a run to a detached shop, a well line or sprinklers.

Every year somebody in Tucson puts a bucket tooth through a gas line or a fiber bundle because the trench was only going to be a couple of feet deep and the ground looked empty. The ground never looks empty. Arizona 811 exists so the utilities can tell you what is under your dig before the machine arrives.

This guide walks through the whole process the way we run it on our own jobs: what to mark, when to call, how long the marks last, what the colors mean, how close you can dig with a machine, and what 811 does not cover. It applies to a homeowner planting a tree as much as to a crew running a 300-foot trench.

What is Arizona 811 and who has to call?

Arizona 811 is the statewide one-call system created under Arizona's underground facilities law. You contact it by dialing 811 or by filing a request online at arizona811.com. The center passes your request to every member utility with lines near the address, and each one sends a locator to mark what it owns.

Anyone who excavates is expected to request a locate first. That includes contractors, landscapers, fence installers and homeowners. The practical rule is simple: if a shovel, auger, trencher or excavator is going into the ground beyond the shallowest surface scraping, put the request in.

When we dig for you, we file the request in our name and manage the tickets, so you are not left holding the paperwork. Our electrical trenching and utility trenching jobs start the same way every time: locate request first, machine second.

How do you white-line the dig area?

White-lining means outlining the proposed excavation in white paint, white flags or white stakes before the locators arrive. Without it, a locator has to guess how far your dig runs and may mark too little, or may call you to ask. Arizona's statute requires excavators to white-line; the only exemption is an owner or occupant digging on their own single-family property.

Even if you are exempt, do it anyway. A clear outline is inexpensive insurance against a missed or partial marking. Here is how to do it well:

  • Use white marking paint on dirt, gravel and pavement, and white flags or stakes where paint will not show.
  • Outline the full width of the trench or hole, then add a line or arrow along its entire length so nobody has to interpret the corners.
  • For a long run, mark the start, the end and every turn, and write the address or ticket number on a stake if you can.
  • Photograph the white-lining with a landmark in the frame, such as the meter, a gate or a corner of the house. You will want it if marks are disputed later.

How many days do you have to wait, and how long do the marks last?

File the request at least two full working days before the dig. Weekends and legal holidays do not count, so a request filed Friday afternoon is not ready for a Monday start. When you plan a trench, build that wait into the schedule instead of treating it as a surprise.

Marks stay valid for 15 working days. A project that stretches past that window, for example a custom home where the pad is cut now and the utility trench is dug a month later, needs a fresh request before the old marks expire. Re-request early, because the new two-working-day wait applies again.

A realistic Arizona 811 timeline for one dig.
StepTimingWhat you do
White-line the digBefore or when you fileOutline the area in white; photograph it
Request the locateAt least two full working days before diggingCall 811 or file at arizona811.com
Utilities respondDuring the waitLocators mark lines or report no conflict
Verify responsesBefore the first cutConfirm every utility has marked or cleared
DigWithin 15 working days of the marksHand-expose inside 24 inches of any line
Re-requestBefore marks expireFile again if the job runs long

How do you check that every utility has responded?

The most common mistake we see is starting when the first marks appear. Several utilities may have lines near one address: electric, gas, water, sewer, telephone and cable or fiber. Each responds on its own schedule, and some answer by marking, others by telling the center they have nothing in your area.

Before the first cut, review the response list attached to your request and compare it to what you see on the ground. If a utility you expect, such as the gas company at a house with a gas meter, has not responded, do not dig near that side of the property. Call the center, ask for a follow-up, and wait.

Walk the whole dig line. Look for a meter, a pedestal, a valve cover, a cleanout or a pull box that sits inside your outline with no mark leading to it. Those are clues that something is buried there. If the surface says one thing and the paint says another, stop and ask.

What do the Arizona 811 marking colors mean?

Marks follow a uniform color code used nationwide. Learn it once and every flag and paint line on your property becomes readable.

ColorWhat it marks
RedElectric power lines, cables and conduit
YellowGas, oil, steam and other flammable material
OrangeCommunications, alarm and signal lines, including fiber and cable
BluePotable water
GreenSewer and drain lines
PurpleReclaimed water
WhiteProposed excavation (your outline)
PinkTemporary survey marks

A mark shows the approximate horizontal route of a line, not its exact position and not its depth. Treat the paint as a corridor. Depth varies with grading changes, past digging and how the line was installed, which is the reason for the hand-digging rule in the next section.

How close can you dig with a machine to a marked line?

Inside 24 inches of a marked line, expose it with hand tools. That means a shovel, a probe or a vacuum tool, not a bucket or a trencher. The goal is to see the actual line and its depth before any machine gets near it.

On our jobs, crossings are the main place this matters. A new electrical trench to a detached garage may cross a water service or a communications line. We hand-expose each crossing, note the depth, and then dig the rest with the machine, keeping the bucket clear of what we found. Hand-exposing is slow, which is why a trench with many crossings costs more than a clean run; see our guide on what trenching costs for what drives that.

Digging parallel to a line is the other trap. Marks give you a horizontal line, and a machine that drifts a foot while cutting a long trench can end up directly on top of it. Keep the white-line and the paint in view of the operator, and have someone on the ground when a trench runs alongside a mark.

Why will 811 not mark the lines on my own property?

Utilities mark what they own. They do not mark private, customer-owned lines, and in a typical Tucson yard those are numerous: the feeder from the house to a detached garage or shop, a well line and pump wire, a gate operator circuit, yard lights, a pool equipment run, sprinkler mains and a septic line. This is practice, not a loophole in the statute, but it is how the system works.

That gap is where most surprise strikes happen. You get the 811 tickets back, see marks only near the street and meter, and assume the backyard is clear. It may hold a buried line from a project the previous owner did without a permit.

  • Check the as-built drawings or permit records if you have them, and ask neighbors or the previous owner about shops, wells and RV hookups.
  • Hire a private locator when the dig crosses any area with a known or suspected private line.
  • Hand-dig test holes at likely crossings before running a machine.
  • Treat any unexpected conduit, pipe, tape or sand layer as a live line until proven otherwise.

What should you do if you hit a line?

Stop the machine, shut it down and get everyone clear. Do not try to push a cut line back into the ground, wrap it with tape, or keep digging to see what you hit. If you smell gas, hear a hiss or see sparks or exposed conductors, leave the area on foot and call 911, then notify the utility and 811.

For damage that is not an emergency, such as a cut irrigation line or a nicked telecom cable, notify the owner of the line and wait for them. Take photographs of the hole, the line and your white-lining and keep your ticket number. Those records show what was marked, when and by whom.

The duties differ a little by who is digging. A contractor carries the responsibility for the locate request, the white-lining, the hand-digging near marks and the notification. A homeowner digging alone is exempt from white-lining, but is not exempt from the danger and may still be on the hook for the repair. If you would rather not carry that risk, our mini excavator and backhoe crews handle the locate and the dig together.

When should you hire a contractor instead of digging yourself?

A fence post hole with a hand auger in an area that the locators cleared is a reasonable DIY job. A trench longer than a few feet, a trench that crosses a driveway or any dig near a meter, a gas line or a visible utility is where a contractor earns the fee.

Send us photos of the area and tell us the length, rough depth and where the trench has to end. We will handle the 811 request and the white-lining, coordinate with your electrician or plumber, and dig to the right depth. You can sketch the route with the trench calculator first to see how much material the job involves.

Questions we get about this

How far ahead do I have to call 811 in Arizona?

Request the locate at least two full working days before you plan to dig. Weekends and legal holidays are not counted as working days, so a Friday request for a Monday start is too late. File online at arizona811.com or call 811, and give yourself extra time for long or complicated routes.

How long are 811 marks good for?

In Arizona the marks are valid for 15 working days. If your dig will continue past that, file a new request before the old marks expire so that the utilities can re-mark, and remember the two-working-day wait starts again. Marks that have faded or been driven over should be refreshed as well.

Do I have to white-line if I am digging my own yard?

An owner or occupant digging on their own single-family property is the one exemption from white-lining. It is still smart to mark the area in white, because the locators then know exactly where you plan to dig and are less likely to mark too little or call you with questions.

Will 811 locate my well line or the wire to my shop?

No. Utilities do not mark private, customer-owned lines such as the feeder from the house to a detached garage, well lines, gate operators, yard lights or sprinklers. These need a private locator, as-built drawings or careful hand-digging. The tickets you get from 811 cover only the utilities' own facilities.

Can I use a machine right next to a marked line?

No. Within 24 inches of a marked line you must expose the line with hand tools, such as a shovel or a vacuum tool. After you have seen its position and depth you can dig further with a machine, but keep the bucket clear of the exposed line and watch for drift on long trenches.

What does a yellow flag or red paint line mean?

Yellow marks gas, oil or steam lines, and red marks electric. Orange is communications, blue is potable water, green is sewer or drain, purple is reclaimed water, white is the proposed excavation and pink is temporary survey marking. The marks show an approximate route, not exact position or depth.

Sources

Rules change. Check the agency source before you rely on a number for your job.

Have a project? Get a quote

Tell us what you need and send a few photos. Photos of the route, the access and the ground let us price most jobs without a site visit.

Photos (optional · up to 3 · 7 MB total)
Best way to reach you

We use your details only to answer this request. See our privacy policy.